The steps between choosing a contractor and letting them start: contract execution, bonds, insurances, programme acceptance and handing over the site.
Award is a decision, not an appointment. Between the two sit the contract itself, the security you need in place, the insurances, an accepted programme and the formal handover of the site. Owners who compress this period lose the only moment when the contractor has a strong incentive to agree things, which is before it has been paid anything.
Before stage one
Do not notify a preferred bidder until you are ready to execute a contract, because the notification changes the balance of the negotiation. Have the contract conditions, the accepted qualifications, the payment mechanism and the required security drafted and reviewed in advance, so that the period between award and start is measured in weeks rather than months.
- A tender report and a documented decision against pre-agreed criteria.
- Contract conditions reviewed by a licensed Saudi adviser.
- A written schedule of which bid qualifications you accept and which you reject.
- A decision on bonds, guarantees and retention, and the form each will take.
- Confirmation that the site can actually be handed over, including consents and access.
Stage 1: Close out the qualifications
Go through the winning bid assumptions and exclusions one by one and record the agreed position on each: accepted, rejected, or priced. Anything left unresolved becomes a claim in the first months. This is the last point at which the contractor is still competing for the work.
- Deliverable: A signed schedule of clarifications forming part of the contract documents.
- Owner: The cost consultant with the owner and the contractor.
- Approval gate: No open item remains from the bid documents.
Stage 2: Assemble the contract documents
Decide which documents form the contract and in what order they take precedence: the agreement, the conditions, the specification, the drawings, the priced document, the programme and the clarifications. Precedence matters because these documents will eventually disagree with each other, and the contract has to say which wins.
- Deliverable: A contract document list with a stated order of precedence.
- Owner: The licensed adviser with the development manager.
- Approval gate: Every document referenced in the agreement actually exists and is the correct revision.
Stage 3: Fix the payment mechanism
Agree how and when payment is made: valuation dates, what evidence supports a claim for payment, the period for certification and payment, retention percentage and release points, and how any advance payment is recovered. Payment disputes cause more delay than technical ones, and almost all of them come from a mechanism that was never written clearly.
- Deliverable: A payment schedule and mechanism written into the contract, including retention terms.
- Owner: The owner with the adviser and the cost consultant.
- Approval gate: You can state exactly what triggers each payment and when it falls due.
Stage 4: Put the security in place
Obtain the performance bond, the advance payment guarantee if an advance is being paid, and any parent company guarantee, in the agreed form and from an acceptable institution. Check the wording, the value, the expiry and what triggers a call. Security obtained after mobilisation is security you did not really have.
- Deliverable: Original bonds and guarantees held by you, checked for form, value and expiry.
- Owner: The contractor to provide, the adviser to verify.
- Approval gate: No advance payment is made and no mobilisation occurs before the security is held.
Stage 5: Verify the insurances
Confirm that the required policies exist, cover the right parties, carry adequate limits and run for the right period: works insurance, third party liability, workforce cover and the professional indemnity of any designer, including contractor-designed elements. Read the certificates rather than accepting a statement that cover is in place.
- Deliverable: Certificates for each required policy, with limits, deductibles and periods recorded.
- Owner: The contractor and designers to provide, verified on the owner side.
- Approval gate: Each policy covers the project for its full duration, including the defects period where required.
Stage 6: Accept the programme and the key personnel
Review and accept the construction programme, with its logic, milestones and long lead procurement dates, and confirm the named key personnel. Both should be contract documents, because a programme you never accepted is a programme you cannot measure against, and personnel not named can be replaced without discussion.
- Deliverable: An accepted programme and a named key personnel schedule attached to the contract.
- Owner: The contractor to submit, the owner side to accept.
- Approval gate: The programme shows milestones you can actually verify on site.
Stage 7: Execute and hand over the site
Sign the contract, then give possession formally: a dated handover record, a photographic condition survey of the site and its neighbours, confirmed access arrangements and the utility position. The condition survey is what prevents an argument later about damage that was already there.
- Deliverable: A signed contract and a dated site possession record with a condition survey.
- Owner: The owner with the development manager.
- Approval gate: Possession is recorded on a date, because contractual time usually runs from it.
Stage 8: Set up the administration before work starts
Agree the reporting format, the meeting cycle, who may issue instructions and in what form, how requests for information are handled, and the process for variations. For an owner abroad, add the delegated authority limits so decisions do not queue behind your time zone.
- Deliverable: A project administration protocol issued to all parties before the first working day.
- Owner: The development manager.
- Approval gate: Everyone knows who can instruct, in what form, and who reports what to whom.
Handovers between stages
The handover most often botched is from tender analysis into the contract. Qualifications accepted in a meeting, a programme discussed at interview and a specification clarified by email all have to arrive inside the contract documents with a revision and a date. The second is from contract execution into administration: if nobody is formally appointed to administer the contract from day one, instructions are given informally and the mechanisms you negotiated go unused.
How you know it is finished
The appointment is complete when you hold a signed contract with a defined document precedence, original bonds, verified insurance certificates, an accepted programme, named personnel, a recorded site possession with a condition survey, and an administration protocol in circulation. Until all of those exist, the contractor may be on site but your position is weaker than the contract you negotiated.
Domira designs, builds and manages projects across Saudi Arabia for owners who are based abroad: land appraisal, feasibility, design, construction, handover and asset management under one accountable contract. Send us the plot or the brief and Domira will put the numbers in front of you before you commit.
Frequently Asked Questions
What should be in place before a contractor starts on site?
A signed contract with a stated order of precedence between documents, the performance bond and any advance payment guarantee in your hands, verified insurance certificates, an accepted programme, named key personnel, a recorded site possession with a photographic condition survey, and an agreed administration protocol covering instructions and reporting.
Why does the order of precedence of contract documents matter?
Because the documents will eventually contradict each other: a drawing will show something the specification does not describe, or the priced document will differ from both. The order of precedence decides which one governs, which decides who pays. Agreeing it at award costs nothing; arguing about it during construction costs a great deal.
Should the construction programme be part of the contract?
It is generally in your interest for an accepted programme with verifiable milestones to be a contract document, because it gives you something to measure progress against and a basis for discussing delay. How it is incorporated affects the contractor obligations and your own, so have a licensed adviser confirm the drafting rather than simply attaching a chart.