Waterproofing is cheap to install and expensive to repair. The failures below are the ones that surface months after handover.
Waterproofing occupies a tiny share of a construction budget and causes a disproportionate share of post-handover disputes. The reason is timing: it is installed early, covered immediately, and tested by weather long after everyone involved has moved on.
Why these keep happening
These failures share one characteristic: they are all invisible at handover. The building looks finished, the surfaces are dry, and the defect waits for the first sustained exposure to water before announcing itself.
1. Falls and drainage designed after the waterproofing
Slopes look like a finishing detail, so they are often left to be sorted out during screeding.
- Avoid it by: Set out falls and drain positions on drawings before waterproofing, with minimum slopes specified toward outlets.
- Proof it is closed: A levels drawing showing falls and outlets, verified on site with a spirit level before the membrane is covered.
What it costs you: Water ponds on the roof or in the shower instead of draining, and standing water finds every weakness in the membrane.
2. Skipping the flood test
It costs a day, and by that stage in the programme, days feel expensive.
- Avoid it by: Flood test every wet area and flat roof for the specified duration before any covering work begins.
- Proof it is closed: Dated photographs at the start and end of the test, with water level marked and the result recorded.
What it costs you: The test is replaced by the first rain or the first shower, with tiles and ceilings already installed above the failure.
3. Membrane stopped at floor level instead of turned up
Turning the membrane up the wall takes longer and is easy to trim short where the tiler wants a clean edge.
- Avoid it by: Specify the upturn height at wall junctions and inspect it before tiling, particularly behind showers.
- Proof it is closed: Photographs of the upturn at every wet wall junction, taken before tiling.
What it costs you: Water travels up through the wall base at exactly the junction where showers and sinks discharge.
4. Penetrations sealed carelessly
Pipes, drains and fixings are installed by different trades at different times, and nobody owns the junction.
- Avoid it by: Detail every penetration explicitly and require sleeves and collars rather than improvised sealant.
- Proof it is closed: A penetration schedule with each one photographed after sealing and before covering.
What it costs you: Every penetration becomes a potential leak path, and they are the hardest failures to locate afterwards.
5. No protection layer before following trades
The membrane is complete and looks robust, so work continues over it immediately.
- Avoid it by: Install the specified protection layer immediately after the membrane and restrict access until it is in place.
- Proof it is closed: Site instruction recording protection installed on the same day as the membrane.
What it costs you: Trolleys, reinforcement, tools and foot traffic puncture it, and punctures are invisible under screed.
6. Treating internal wet areas as lower risk than roofs
Roof leaks are dramatic, so attention concentrates there.
- Avoid it by: Apply the same specification, testing and documentation to bathrooms, kitchens and laundry areas as to roofs.
- Proof it is closed: A flood test record for every wet area, not only for the roof.
What it costs you: Bathroom leaks damage ceilings and finishes below and are frequently misdiagnosed as plumbing faults for months.
A short check before you sign
- Are falls and outlet positions drawn and checked before the membrane goes down?
- Has every wet area and flat roof been flood tested with a dated record?
- Is the membrane turned up at wall junctions to the specified height?
- Is every penetration detailed, sealed and photographed?
- Was a protection layer installed before other trades worked over it?
If it has already happened
If a leak appears after handover, resist the instinct to open the ceiling first. Establish where water is arriving, then test upstream systematically: isolate supply pipes, flood the suspected area, and observe. Opening finishes without a hypothesis usually produces damage without a diagnosis, and it is the fastest way to turn a contained defect into a large repair.
If you are preparing to build, Domira can review your drawings, scope and contractor offers before you commit, and supervise delivery against the programme and specification you agreed.
Frequently Asked Questions
How long should a flood test run?
Long enough for water to find a path, which for practical purposes means a sustained period of standing water rather than a brief fill and drain. Specify the duration in the contract, require the water level to be marked and photographed at start and finish, and treat a drop in level as a failure until it is explained.
Is liquid applied or sheet membrane better?
Both perform well when installed correctly, and both fail at details rather than in the middle of a flat surface. Liquid systems handle complex geometry and penetrations more easily, while sheet systems offer consistent thickness. The decision matters less than the quality of detailing at upturns, corners and penetrations.
Should waterproofing be covered by a warranty?
Yes, and it should be a written product and installation warranty naming the system, the applicator and the period. Keep it in the handover file with the test records, because a warranty without evidence of correct installation and testing is difficult to rely on when a claim is made.