Multi-unit construction rewards repetition and punishes variety. Where the money concentrates when you build to rent or sell.
A villa is built once for one household. An apartment block is the same work repeated, which changes the economics completely: every inefficiency multiplies by the number of units, and every standardisation pays back the same number of times.
What this number does and does not include
This covers construction of a residential building with multiple units on an owned plot. Land, financing, marketing and operating costs sit outside it, as do the professional fees the owner pays directly.
Structure and grid regularity
The frame carrying repeated floors, where a regular column grid allows formwork and reinforcement patterns to be reused floor after floor.
- Pushes it up: Irregular layouts between floors, transfer structures over open ground floors, and long spans introduced for layout flexibility.
- Brings it down: Vertical alignment of columns and walls, and a unit layout that repeats identically on every typical floor.
- How to control it: Test the structural grid against the unit mix at concept stage. A grid that suits the units saves more than any later procurement effort.
Unit mix and wet area stacking
The arrangement of apartment types and the position of kitchens and bathrooms, which governs the services layout for the whole building.
- Pushes it up: Many different unit types, and wet areas positioned differently on each floor.
- Brings it down: A limited number of repeated unit types with bathrooms and kitchens stacked vertically.
- How to control it: Limit the unit mix to what the market actually absorbs. Every additional type adds design, procurement and construction complexity.
Vertical circulation
Stairs, lifts, lobbies and the shafts they occupy, which consume area that cannot be sold or rented.
- Pushes it up: Multiple cores, oversized lobbies and lift specifications beyond what the building needs.
- Brings it down: An efficient core serving the maximum number of units within acceptable travel distances.
- How to control it: Measure the ratio of sellable area to total constructed area early. A low ratio is a permanent tax on every future transaction.
Services distribution
Risers, distribution boards, water tanks, pumps and the metering arrangement for individual units.
- Pushes it up: Scattered risers, individual systems where central would serve, and metering arrangements decided after first fix.
- Brings it down: Consolidated risers and a metering strategy chosen before services design begins.
- How to control it: Decide early whether units are individually metered and serviced, since this shapes the entire distribution design.
Finishes at scale
Flooring, joinery, sanitary ware and kitchens repeated across every unit.
- Pushes it up: Varying specifications between units, late changes, and materials that cannot be reordered consistently.
- Brings it down: One specification per unit type, bought in volume, with a small allowance for premium units if the market rewards it.
- How to control it: Fix finishes before the first unit is finished, because changes mid-way create two standards in one building and complicate maintenance forever.
Common areas and external works
Entrance lobby, corridors, parking, landscaping and the building services that serve everyone.
- Pushes it up: Elaborate lobbies, extensive landscaping and parking arrangements requiring structural work.
- Brings it down: A well-finished entrance and simple corridors, since the entrance is what tenants and buyers judge.
- How to control it: Concentrate common area budget at the entrance and the parking access, which are the two spaces everyone uses daily.
Programme and preliminaries
Site overheads, cranes, access and management across a duration measured in many months.
- Pushes it up: Extended programmes, sequential rather than parallel working, and interruptions for decisions.
- Brings it down: Floor-by-floor cycles that allow following trades to start on completed floors while the structure continues above.
- How to control it: Design for a repeating floor cycle. The speed of that cycle governs both the programme and the preliminaries bill.
Costs that never appear on the first page
- Utility connection capacity for the whole building, which is a different order of cost from a single villa.
- Fire safety systems and their commissioning and certification.
- Lift supply, installation and the statutory inspection that follows.
- Temporary power and water across a long programme.
- The cost of unsold or unrented units during lease-up, which is a real project cost even though it appears after construction.
Keeping the budget honest
Budget per unit and per square metre of sellable area at the same time. The first tells you whether the units work commercially, the second tells you whether the building is efficient. A project can pass one test and fail the other.
- At concept, when grid and unit mix are still flexible.
- After the services strategy is set, since metering and distribution are hard to change later.
- Before finishes are ordered, when volume pricing is available.
- At the end of the first completed floor, when the real cycle time and cost per unit become measurable.
If you are preparing to build, Domira can review your drawings, scope and contractor offers before you commit, and supervise delivery against the programme and specification you agreed.
Frequently Asked Questions
How many unit types should a building have?
As few as the market allows. Each additional type multiplies design work, procurement lines and construction variation. Two or three well-chosen types usually serve demand better than six that each require their own drawings, kitchens and joinery.
Is it worth building a higher specification to attract better tenants?
Only where tenants can see and use it. Better kitchens, bathrooms and entrance lobbies affect rental decisions; concealed upgrades generally do not. Direct the premium to the parts of the building that are experienced daily.
What is a good sellable to constructed area ratio?
It depends on building type and local requirements, particularly parking and circulation, so a universal figure is misleading. What matters is measuring it during design and comparing options, because the ratio you accept at concept stage stays with the building for its whole life.