A practical launch and sales sequence for a small Saudi project, from price list and materials to release strategy, follow-up discipline and closing the last units.
A small project sells out through preparation rather than through a launch event. The sequence is: fix the product and the price list, prepare material that answers buyer questions, choose and brief the channel, release units in a controlled order, then measure enquiries and conversions weekly and adjust. Most projects that stall did not have a demand problem; they had no way of knowing where buyers were dropping out.
Before stage one
Do not start marketing until the product is fixed and the documentation matches it. Changing areas, finishes or prices after launch costs credibility with exactly the buyers who moved fastest, and those are the people you need to speak well of the project.
- A final unit schedule with areas on a stated basis, matching the permitted drawings.
- A signed price list with floor prices and a written discount policy.
- The sale contract and payment plan approved by a licensed adviser.
- A named person responsible for responding to every enquiry within a stated time.
- Confirmation that any approval required before marketing units has been obtained.
Stage 1: Define the buyer you are selling to
Write down who buys this unit and why: a family upgrading within the district, a first-time buyer with financing, an investor buying to let, or a company buying staff accommodation. Each group needs different information and responds to different things. A brochure written for everybody persuades nobody, and a sales team without a defined buyer will chase whoever calls.
- Deliverable: A one-page buyer profile per unit type, with the reason each would buy.
- Owner: Developer with the sales lead.
- Approval gate: Material is only written after the profiles are agreed.
Stage 2: Fix the price list and the payment plan
Set prices unit by unit, reflecting floor, aspect, layout and any private outdoor space, then set a floor price and a written discount policy. Decide the payment plan and know what it costs you: a plan with most money at completion is attractive to buyers and worth less to you than it looks. Keep one authoritative price list, held by one person.
- Deliverable: A dated price list with unit prices, floor prices and the approved payment plan.
- Owner: Developer.
- Approval gate: Any price change is issued as a new dated list, never verbally.
Stage 3: Prepare material that answers real questions
Buyers ask about area on what basis, service charges, parking, what is included in the finish, completion date, payment terms and title. Answer those in writing, with a unit plan, a specification schedule and honest images. Renderings that flatter the building create complaints at handover. A written question and answer sheet for the sales channel prevents invented answers.
- Deliverable: A sales pack: unit plans, specification schedule, payment terms and a question and answer sheet.
- Owner: Developer with the design team.
- Approval gate: Nothing is published that contradicts the permitted drawings or the contract.
Stage 4: Choose and brief the sales channel
Decide between an exclusive agency, a panel of brokers, or your own team, and put the mandate in writing with the fee, the term, the reporting and what the agent must actually deliver. Check that any broker is properly licensed to market real estate. Brief everyone from the same pack, and require enquiries to be logged rather than kept in a personal phone.
- Deliverable: A signed mandate plus an acknowledged briefing pack and enquiry log format.
- Owner: Developer.
- Approval gate: No unbriefed party markets the project.
Stage 5: Release units in a controlled order
Do not put every unit on the market at once. Release a first group, typically the harder units at attractive prices alongside a few good ones, then raise prices as each group sells. This gives you early momentum, real price evidence and the ability to hold the best units for a stronger market. Keep a written release plan so nobody sells a held unit to make a quick commission.
- Deliverable: A release plan showing which units are available in each phase and at what prices.
- Owner: Developer.
- Approval gate: Units outside the current release cannot be offered, reserved or discounted.
Stage 6: Run the launch and capture every enquiry
Whether the launch is an event, a digital campaign or a broker briefing, the measure is enquiries captured with contact details and source. Log the source of every enquiry, because within three weeks you will know which channel produces buyers and which produces traffic, and you can move the budget. Respond to every enquiry within a stated time, because response speed converts better than any brochure.
- Deliverable: An enquiry log with source, date, unit interest and next action for each entry.
- Owner: Sales lead.
- Approval gate: No enquiry older than the agreed response time is left without contact.
Stage 7: Convert, document and keep momentum
Move buyers from interest to reservation to signed contract with a documented process: reservation terms in writing, a deadline, the contract issued promptly and the payment schedule confirmed. Publish progress internally each week: enquiries, viewings, reservations, contracts and cancellations. A reservation that has not converted in the agreed period returns the unit to the market.
- Deliverable: A weekly sales report showing the funnel and the current available list.
- Owner: Sales lead with the developer.
- Approval gate: Reservations expire automatically unless extended in writing.
Stage 8: Close the last units deliberately
The final units are usually the least attractive, and they decide your margin because the cost is already spent. Plan for them: a targeted incentive such as a finished upgrade or a parking space rather than a general price cut, a bulk sale to an investor, or holding them to let if the cash allows. Decide the plan before you are down to the last three, not after.
- Deliverable: A written plan for the remaining stock, with a decision date.
- Owner: Developer.
- Approval gate: Any general price reduction requires the owner written approval.
Handovers between stages
The buyer profiles determine the material, the material determines what the channel can promise, the release plan determines what they may offer, and the enquiry log determines where the budget goes next month. Each handoff is a document. Where a project has a shared price list, a written release plan and a single enquiry log, the sales process can be managed from abroad with a weekly call.
How you know it is finished
The launch phase is complete when you can state, from the log rather than from memory, how many enquiries each channel produced, the conversion rate to reservation and to contract, the average achieved price against the list, and what stock remains. That information is also the most valuable thing you take into your second project.
Domira designs, builds and manages projects across Saudi Arabia for owners who are based abroad: land appraisal, feasibility, design, construction, handover and asset management under one accountable contract. Send us the plot or the brief and Domira will put the numbers in front of you before you commit.
Frequently Asked Questions
Should I release all units for sale at launch?
Usually not. Releasing in controlled groups lets you build momentum, generate real price evidence and raise prices as the better units come to market, and it stops the whole scheme being judged against the weakest unit. Keep a written release plan so nobody offers a held unit, and review the plan after each group sells rather than on a fixed calendar.
How do I measure whether a property launch is working?
Track the funnel weekly: enquiries by source, viewings, reservations, signed contracts and cancellations, plus achieved price against list price. A launch with enquiries but no viewings has a pricing or product problem. Viewings without reservations usually means the payment terms, the specification or the completion date is the obstacle. The numbers tell you which conversation to have.
What is the best way to sell the last few units in a development?
Prefer targeted incentives over general price cuts, because a public reduction devalues the units you already sold and tells the market to wait. Options include upgrading a finish, including parking or a year of service charges, packaging remaining units for an investor, or holding them to let if your cash flow allows. Decide the approach before the last units are all that remains.