Bonds, Guarantees and Retention: What Each Security Really Costs

Bonds, Guarantees and Retention: What Each Security Really Costs

Domira Team July 10, 2025 6 min read

The security an owner takes on a construction contract, what each instrument protects against, and why every one of them is paid for in the contract sum.

Bonds, guarantees and retention exist so that a contractor failure does not become entirely your problem. Each instrument covers a different failure, each has a cost, and that cost arrives inside the contract sum whether or not you see it. Understanding what each one actually does is how you take enough security without paying for protection you will never use.

What this number does and does not include

This covers the security instruments an owner commonly takes from a contractor on a building contract and the cost consequences of each. It does not cover insurance, which responds to damage and liability rather than to non-performance, and it does not state values or rates, because these are commercial terms negotiated per project. The legal effect of any instrument is a question for a licensed Saudi adviser.

Performance bond

Security against the contractor failing to perform, callable in the circumstances the bond wording allows. It is the instrument most owners think of first and the one whose wording matters most, because the difference between an on-demand instrument and a conditional one decides whether it is useful when you need it.

  • Pushes it up: A higher bond percentage, a longer bond period and a contractor whose bank prices its exposure highly.
  • Brings it down: A shorter period, a lower percentage, and a contractor with a strong banking relationship.
  • How to control it: Fix the wording, the value, the expiry and the trigger before award, and have your adviser confirm what it takes to call it.

Advance payment guarantee

Security for money you pay before work is done. Where an advance supports mobilisation and material orders it can be reasonable, but it is a loan from you, and it should be guaranteed for its full value and reduced as it is recovered from interim payments.

  • Pushes it up: A larger advance percentage and a long recovery period across the contract.
  • Brings it down: A smaller advance, or none at all, and rapid recovery from early valuations.
  • How to control it: Never release the advance before the guarantee is in your hands, and set the recovery schedule in the contract.

Retention withheld from payments

A percentage deducted from each payment and released in stages, typically part at completion and part at the end of the defects period. It is the simplest security because it is your own money, and it is limited: on a serious defect it rarely covers the remedy.

  • Pushes it up: A higher percentage and a longer holding period, both of which the contractor prices into its rates.
  • Brings it down: A lower percentage, an earlier release or substitution by a bond.
  • How to control it: State the percentage, any cap, and the exact release points, and keep the retention ledger reconciled every month.

Retention bond in place of cash retention

A bond provided instead of withholding cash, which improves the contractor cash flow and can reduce its pricing. You exchange money in your hand for a claim against an institution, which is better or worse depending on the wording and the institution.

  • Pushes it up: A larger value and a longer period, and any requirement for an on-demand instrument.
  • Brings it down: A shorter period and a contractor with good banking terms.
  • How to control it: Compare the price reduction offered against the practical difficulty of calling a bond versus applying cash you already hold.

Parent company guarantee

An undertaking from the contractor parent to perform the obligations if the subsidiary does not. Useful where you are contracting with a local entity of a larger group, and worth very little if the parent is itself thinly capitalised.

  • Pushes it up: Nothing directly, since it is an undertaking rather than a purchased instrument.
  • Brings it down: Not applicable, though a parent may resist giving it at all.
  • How to control it: Check the financial standing of the guarantor, not just its name, and have the wording reviewed by your adviser.

Defects and maintenance security

Security that survives completion, whether as the second tranche of retention, a bond extending through the defects period, or a maintenance obligation with its own guarantee. Its value is that it keeps a contractor engaged after it has left your site.

  • Pushes it up: A longer defects period and extensive services requiring maintenance attendance.
  • Brings it down: A short defects period on a simple building with few systems.
  • How to control it: Align the security expiry with the end of the defects period, and diarise the release date so it is not simply forgotten.

Your own cost of holding security

Administration that owners rarely count: checking wording, tracking expiry dates, agreeing releases, reconciling the retention ledger and handling extensions when the programme lengthens. Small in money, and the source of real loss when a bond lapses unnoticed.

  • Pushes it up: Many instruments, several parties and a project with an extended or uncertain programme.
  • Brings it down: A small number of instruments with clearly diarised expiry dates.
  • How to control it: Keep one register of every instrument with value, trigger and expiry, reviewed at each monthly report.

Costs that never appear on the first page

  • The contractor cost of providing bonds, recovered inside its rates whether or not you see it.
  • A price premium where the bond period is long or the wording is aggressive.
  • Extension fees on bonds when the programme runs beyond the original expiry.
  • The working capital effect on a contractor of heavy retention, which can show up as slower progress.
  • Legal fees to review non-standard wording proposed by a bank or a contractor.
  • The value of security lost entirely when an instrument expires before a defect is discovered.

Keeping the budget honest

Take the security you would actually use and no more, because everything you demand is priced. A moderate performance bond with usable wording, an advance guarantee if there is an advance, and retention with clearly defined release points cover most realistic failures. Layering every available instrument on a modest project increases the contract sum and reduces the pool of contractors willing to bid.

  • At award, checking wording, values, triggers and expiry dates for every instrument.
  • Before releasing any advance payment, confirming the guarantee is held.
  • At each monthly valuation, reconciling the retention ledger.
  • Whenever the programme is extended, confirming bonds have been extended too.
  • At completion and at the end of the defects period, at each scheduled release.

Domira designs, builds and manages projects across Saudi Arabia for owners who are based abroad: land appraisal, feasibility, design, construction, handover and asset management under one accountable contract. Send us the plot or the brief and Domira will put the numbers in front of you before you commit.

Frequently Asked Questions

What is a performance bond in a construction contract?

It is security provided by the contractor, usually through a bank, that you can call in the circumstances its wording allows if the contractor fails to perform. The value, the period and above all the wording determine whether it is useful in practice, so agree all three before award and have a licensed adviser confirm what would be required to call it.

How does retention work on a construction project?

A percentage is deducted from each payment and held, typically with part released at completion and the balance at the end of the defects period. It keeps the contractor engaged on finishing and on defects. The percentage, any cap and the release points are contractual terms, and applying retention to fix problems must follow the contract mechanism.

Do bonds and guarantees increase the price I pay?

Yes, always, because the contractor pays its bank for them and recovers that cost in its rates, and because aggressive wording or long periods carry a premium. That is not a reason to take no security, it is a reason to take the security you would actually use and to keep the periods aligned with the risks they cover.

Complimentary Consultation

Have a Property Question?

Domira can help you navigate property, financing and investment decisions in Saudi Arabia. Speak with our team for an initial consultation.