Facade panels fail at their fixings. Brackets with no adjustment, no allowance for expansion and the wrong metals in contact are the faults that recur.
Facade panels and aluminium framing are fixed to a structure that was built to a construction tolerance, in a climate where a dark metal panel can swing through a very large temperature range every day. The failures are consistent: brackets without enough adjustment to absorb structural inaccuracy, fixings that prevent the panel from expanding, dissimilar metals in contact, and a penetration through the wall that nobody sealed. All of them are decided at the fixing, not in the panel.
Why these keep happening
The underlying issue is that the facade is designed as a system and installed as a set of components by a subcontractor working to a tight rate. The system design assumes adjustable brackets set out from a survey, sliding and fixed points arranged so each panel can move, isolation between metals and a sealed interface with the building. On site, where a bracket will not reach, something gets packed, drilled or welded, and the system assumption quietly disappears.
1. Setting out from the structure instead of from a survey
Concrete is built to a tolerance and is never as accurate as a facade needs to be. A cladding system set out by measuring from the slab edge as built inherits every deviation, and the panel lines then wander visibly across the elevation. A survey of the actual structure, against which the bracket positions are calculated, is how a facade ends up straight.
- Avoid it by: Survey the as built structure before fabrication and set out the system from control lines rather than from the concrete face.
- Proof it is closed: A facade setting out survey with control lines and bracket positions, approved before fabrication.
What it costs you: Visibly uneven panel lines, panels that do not fit at the end of a run, and remedial work on a finished facade.
2. Using brackets with no real adjustment
Adjustable brackets exist so the installer can absorb structural deviation in three directions without packing or improvising. Systems supplied with minimal adjustment, or installed with the adjustment already used up, leave the installer with no option but to shim, bend or cut, each of which changes the load path the designer calculated.
- Avoid it by: Specify brackets with adjustment appropriate to the measured structural tolerance and verify the range at the mock up stage.
- Proof it is closed: Bracket type and adjustment range recorded, with the mock up demonstrating installation over the actual deviation.
What it costs you: Improvised fixings of unknown capacity and a facade whose performance no longer matches its design.
3. Fixing every point rigidly and leaving no room for expansion
Aluminium and steel expand measurably when heated, and a long run of framing or a large dark panel in direct sun moves. A system needs defined fixed points and sliding points so the movement goes where the designer intended. Bolting everything tight produces buckling, noise, cracked sealant and fixings working loose.
- Avoid it by: Follow the system fixed and sliding point arrangement, use slotted holes where specified, and resist the instinct to tighten everything.
- Proof it is closed: An installation inspection confirming sliding points remain free, with photographs of slotted connections.
What it costs you: Distorted panels, failed sealant joints, audible movement and fixings that loosen progressively.
4. Putting dissimilar metals in direct contact
Aluminium in direct contact with other metals, in the presence of moisture, can corrode galvanically, and coastal air accelerates it. Carbon steel brackets, mismatched fasteners and swarf left from drilling all cause it. The corrosion starts at the fixing, which is the one place you cannot inspect once the panel is on.
- Avoid it by: Use compatible metals and the isolation washers or pads the system requires, and clean all drilling swarf from the facade.
- Proof it is closed: A fixings schedule stating materials and isolation, with inspection of isolation components before panels are closed.
What it costs you: Corroded fixings that lose capacity invisibly, staining on the facade, and panel replacement.
5. Drilling the structure wherever it is convenient
Facade fixings transfer wind load and panel weight into the structure, so the anchor type, embedment, edge distance and the condition of the concrete all matter. Drilling close to a slab edge, into a region of congested reinforcement, or cutting a bar to make a hole fit, undermines both the fixing and the structure.
- Avoid it by: Use the approved anchor with its specified embedment and edge distance, scan for reinforcement before drilling and record any deviation.
- Proof it is closed: Anchor approval, pull out test results at the specified frequency and a record of any position changed on site.
What it costs you: Anchors with far less capacity than assumed, cracked slab edges and a structural question on a completed facade.
6. Treating the facade as the only line of defence against water
Most modern cladding systems are designed to be drained and ventilated, which means water that gets behind the panel is expected and must be able to drain out. If the cavity drainage is blocked, the flashings are missing or the penetrations through the backing wall are unsealed, that water enters the building instead.
- Avoid it by: Install the flashings, cavity barriers and drainage paths as drawn, and seal every penetration through the backing wall.
- Proof it is closed: Inspection of drainage paths and flashings before panels are closed, plus a water spray test on a sample area.
What it costs you: Water ingress through a facade that appears intact, with leaks that are extremely hard to trace.
7. Omitting the mock up and the pull out tests
A facade is the most expensive and least accessible part of a building. A mock up proves the system can be installed over the real structural deviation, that the details work and that the appearance is acceptable. Anchor pull out tests prove the fixings achieve their design capacity in the actual concrete. Skipping either means finding out at height, on the finished elevation.
- Avoid it by: Build a mock up including a difficult junction, and carry out anchor tests at the frequency the specification requires.
- Proof it is closed: A signed mock up approval and anchor test reports with positions and loads recorded.
What it costs you: Discovery of a systemic fixing problem after a large area is installed, with access costs to put it right.
A short check before you sign
- Facade setting out comes from a survey of the as built structure, not from the concrete face.
- Brackets provide adjustment in three directions suited to the measured deviation.
- Fixed and sliding points follow the system design and sliding points are free to move.
- Dissimilar metals are isolated and drilling swarf has been removed.
- Anchors match the approval for type, embedment and edge distance, with pull out tests recorded.
- Flashings, cavity barriers and drainage paths are installed and inspected before closing.
- A mock up has been approved and a water spray test carried out on a sample area.
If it has already happened
If a facade is already installed and showing distortion, noise, staining or leakage, do not start by sealing things. Open a representative panel and look at the fixings, because the diagnosis is almost always there: adjustment used up and packed out, sliding points bolted solid, corroded or incompatible fasteners, or anchors in the wrong position. Have the facade specialist and the structural engineer review the opened area together, and extend the inspection to a sample across every elevation, since a fixing error made by one crew will repeat across its whole work area. Leakage is traced by water testing from the lowest suspected point upwards, not by guessing. The remedy ranges from replacing fasteners and restoring the sliding arrangement through to removing and refixing panels on an elevation, and the access cost usually exceeds the material cost, which is the argument for the mock up that was skipped.
Domira builds and supervises projects across Saudi Arabia, and this is the level of detail its site teams work at. Send the drawings or the site, and Domira will tell you what the specification has to say before anyone prices it.
Frequently Asked Questions
Why do cladding panels make noise in the heat?
Because they are expanding and contracting against fixings that will not let them move, so the panel or the framing slips suddenly against the fixing and clicks or bangs. The cause is usually that sliding points were bolted tight, slotted holes were not used, or the fixed and sliding arrangement in the system design was not followed during installation.
What is galvanic corrosion in a facade?
It is corrosion that occurs when two dissimilar metals are in electrical contact in the presence of moisture, with one metal corroding preferentially. In facades it typically affects aluminium in contact with other metals, and coastal air accelerates it. Prevention is by using compatible materials, fitting the isolation washers or pads the system specifies, and removing drilling swarf.
Should facade anchors be pull out tested?
Yes, at the frequency the specification sets, because an anchor capacity depends on the actual concrete, the hole preparation and the installation, not only on the product data. Testing a sample across the elevations confirms that the installed fixings achieve the design load. Record the positions and loads, since they become part of the facade compliance evidence.
Why is a facade mock up worth building?
Because it proves, before the main installation, that the system can be installed over the real structural deviation, that the junction details work, that water drains as intended and that the appearance is acceptable under natural light. The alternative is discovering a systemic problem at height on a finished elevation, where access alone can cost more than the mock up would have.